2024-05-27-investment-decision-rwe-to-build-wind-farms-with-capacity-of-16-gw-jxl3s

RWE has secured the final investment decision for its 1.6 GW Nordseecluster offshore wind projects in the German North Sea, advancing its €20bn investment strategy.

📈 Project Highlights:

– Two-phase implementation

– Construction starts in 2027, operational by 2029

– Power supplied to Germany’s industrial customers

⚡ €20bn Offshore Wind Investment:

– Part of RWE’s €55bn investment strategy for 2024-2030

– Aim to boost offshore wind capacity from 3.3 GW to 10 GW by 2030

🏦 Key Contracts:

– Vestas: Turbines (V236-15.0 MW)

– Atlantique Offshore Energy: Transformer substations

– Hellenic Cables: Cable manufacturing

– Dajin Offshore: Foundation manufacturing